|
|

Top |
WHAT
PRODUCTION CAN BE EXPECTED? |
|
Due to the wide array
of additives, equipment available and varying roadway distress
addressed using Full Depth Reclamation (FDR) , it is difficult
to suggest a single expected production rate. Production rates
may vary from 300sy/hr to 1,200sy/hr, on average, based on variables
such as pavement composition, depth of material and gradation. |
| |

Top |
H0W
SOON CAN YOU DRIVE ON RECLAIMED MATERIAL? |
|
With the new breakthroughs
in chemical stabilizers alone and in combination with bituminous
additives, cure times can be greatly reduced, allowing moderate
traffic to resume only minutes after compaction. Traffic can
also be maintained during the process with adequate project
management. |
| |

Top |
HOW
DO YOU DETERMINE WHAT (IF ANY) ADDITIVE(S) SHOULD BE USED? |
|
In recent years, we
have examined economic and engineering guidelines for the evaluation,
including proper in-situ mix designs, of selected additives.
Guidelines for selecting stabilizing additives are available
for viewing in the new Full Depth Reclamation brochure available
through your local ARRA Contractor Member. (Note: A properly-engineered
mix design in conjunction with both on-site construction monitoring
and the contractor's experience, all culminate in the proper
additive selection). |
| |

Top |
HOW
LONG WILL RECLAIMED ROADS LAST? |
|
As with any typical
road construction project (either new or reconstruction), proper
design and project construction monitoring is of utmost importance
to assure a life-cycle representative of the design. With those
elements in place, a reclaimed road should have the same life-cycle
expectancy as a road constructed with virgin materials. |
| |

Top |
EXPLAIN
THE DIFFERENCE BETWEEN CIR AND FDR. |
|
The main difference
between Cold In-Place Recycling (CIR) and Full Depth Reclamation
(FDR) is that FDR incorporates both the bound asphaltic layers
and a predetermined portion of the underlying base materials
used in the initial construction. CIR incorporates only the
bound asphaltic layers for recycling. Therefore, FDR is the
only methodology other than total reconstruction which addresses
base deficiencies. |
| |

Top |
CAN
YOU RECLAIM A ROAD ABSENT ANY EXISTING ASPHALT (i.e. GRAVEL
ROADWAYS)? |
|
Yes. Bituminous and
chemical (cement, lime, calcium chloride, fly ash, etc.) stabilization/reclamation
can be utilized solely or in combination as methods of FDR in
the absence of any in-sitsu asphaltic materials. An asphaltic
surface treatment such as chip seal or overlay should then be
used to "seal off" the reclaimed layer and provide a running
surface for vehicles. |
| |

Top |
EXPLAIN
THE DIFFERENCE IN TERMINOLOGY BETWEEN SOIL STABILIZATION AND
FULL DEPTH RECLAMATION. |
|
Soil stabilization can
be defined as a chemical or mechanical treatment designed to
increase or maintain the stability of a mass of soil or otherwise
to improve its engineering properties. FDR incorporates or reclaims
in-sitsu pavement materials installed in the initial construction
and/or through the years of improvements and blends those materials
together to re-establish pavement layer integrity. |
| |

Top |
EXPLAIN
THE DIFFERENCE IN COST OF FDR vs. CONVENTIONAL RECONSTRUCTION
METHODS. |
|
Substantial savings
may be gained on any given project. FDR utilizes all or nearly
all in-sitsu materials in-place and minimal supplemental materials
are delivered to the site. There we also cost-savings in the
mining of virgin materials needed for conventional reconstruction,
as well as benefits reflected in time savings and environmental
concerns, which make FDR even more attractive than conventional
reconstruction. |
| |

Top |
CAN
MY EXISTING ROAD BE WIDENED USING FDR METHODOLOGY? |
|
Yes. It is common to
widen using FDR by incorporating shoulder material into the
pulverized roadway materials. One can, through FDR, create a
homogeneous reclaimed base material throughout the pavement
cross section by utilizing the pulverized material of the interior
of the roadway and pushing this material into the excavated
areas of widening. Supplemental aggregates could also be incorporated
to adjust the desired depth and gradation of the recycled mat. |
| |

Top |
CAN
FDR BE PERFORMED ON AN EXISTING CURB/GUTTER STREET? |
|
Yes. However, material
management inside the curbs becomes a critical issue in both
the bid/design construction of the improvements. Consideration
should be given to the geometry of the roadway prior to and
after FDR to evaluate the need to remove or add material so
that the reclaimed material and new surface course meet the
existing gutter. Removal of surplus material and a thicker than
normal leveling course should be considered as part of the project.
A design/construction suggestion would be to remove material
after pre-pulverization to insure adequate blending of the bound
asphaltic materials with underlying granular materials. This
practice will retain the value of the residual asphalt binders
in the upper layers. |
| |

Top |
WHAT
TYPES OF PROBLEMS CAN FDR CORRECT? |
|
FDR is an option to
improve a wide variety of pavement distress signs. Some of the
distress signs that FDR can fix are frequent deep cracking (transverse
or lateral), reflective/alligator cracking, heavy pothole patching,
severe rutting/shoving, parabolic shape and insufficient base
strength. The key to FDR is that all the distress types mentioned
above are eliminated by pulverization and subsequently strengthened
with available stabilizers, if required. |